Transmission System
topic on 2 shows · 4 statements across 4 episodes
4 statements about Transmission System, every show
Wong: Transmission interconnection studies take 6-9 months and cost $250K
“I think most utilities are talking about six to nine months to perform one of those studies, and it's a one-time, right, so risk of restudies will compound that, and it does cost internal utility, typically a hundred, A couple of 100,000 dollars. The typical b…”
Lubbershane: Dynamic line ratings will see increasing adoption across transmission lines
“But I am hopeful, and I do think that there are going to be increasing numbers of transmission lines and regions where, you Adding dynamic line ratings makes more and more sense to ring as much value as is really physically possible out of the transmission sys…”
DOE Study: Grid Must Accommodate 3-4x Renewable Increase in a Decade
“According to a study released in February by the Department of Energy, the transmission system needs to accommodate a three to four X increase in renewable electricity in about a decade, and boy, oh boy, is that going to be difficult.”
Atkinson: Distribution utilities lack systems to handle FERC 2222 energy resources
“It actually mandates that those aggregations are allowed to cross multiple connection points between the transmission system and local grids. And so that actually puts quite a bit of pressure onto distribution utilities to figure out mechanisms that would allo…”