Wong: Transmission interconnection studies take 6-9 months and cost $250K

Josh Wong · Can AI revolutionize grid operations? · Aug 20, 2026 · at 11:07

Josh Wong, CEO of ThinkLabs, discusses the standard duration and cost benchmarks for utility transmission grid impact and interconnection studies.

0:00 / 0:17exact quote · 17.4s
720p mp4 · rendered on demand · StarZero watermark
“I think most utilities are talking about six to nine months to perform one of those studies, and it's a one-time, right, so risk of restudies will compound that, and it does cost internal utility, typically a hundred, A couple of 100,000 dollars. The typical benchmark is about quarter million dollars per study”

quote is from the automated transcript, cleaned for reading: filler sounds and stutters are removed, nothing is rephrased. names can be misheard (the analysis reads context, assessments check outside sources). how →

More from Josh Wong

Assertion Not checkable as stated
Wong: ThinkLabs cuts nine-month grid interconnection studies to under 10 minutes
“So studies that would take previously nine months, right, as I mentioned, interconnection studies, now it takes us only a matter of a couple of minutes, like 10 minutes or less.”
Josh Wong Aug 20, 2026 ▶ 19:30 Can AI revolutionize grid operations?
Opinion
Wong: AI has higher potential upside in grid operations than planning
“I think it is the complete opposite. I think the potential is even higher.”
Josh Wong Aug 20, 2026 ▶ 28:54 Can AI revolutionize grid operations?
Opinion
Wong: The grid has enough latent capacity for most data centers today
“So let me just make a statement here, which is, I believe the grid has enough existing latent capacity to connect the majority, if not all of the data centers today.”
Josh Wong Aug 20, 2026 ▶ 37:27 Can AI revolutionize grid operations?
Assertion Partly supported
Wong: SCE projects up to 10,000 monthly energization requests taking 30-45 days
“I think when we public study that we did with SCE, I think they are projecting like up to 10,000 of these energization requests per month, and each one of them takes like 30 to 45 days.”
Josh Wong Aug 20, 2026 ▶ 12:44 Can AI revolutionize grid operations?
Assertion Not checkable as stated
Wong: ThinkLabs' physics-informed AI models are deterministic and cannot hallucinate
“So our models actually can't hallucinate. It's actually deterministic. You ask it the same thing, it will give you the same answer all the time.”
Josh Wong Aug 20, 2026 ▶ 17:35 Can AI revolutionize grid operations?
Assertion Not checkable as stated
Wong: ThinkLabs trains state-sized utility models in 10 minutes for $5
“And we have done that for multiple large IOUs now, a couple of thousand buses, it takes us about 10 minutes per training run. For a Powerflow model the size of a state, typically. And that 10 minute training run cost maybe five bucks of compute. And we were ab…”
Josh Wong Aug 20, 2026 ▶ 18:46 Can AI revolutionize grid operations?