transformer manufacturing facility

1 statements across 1 episodes · 0 bullish · 0 bearish · 1 people on the record · first statement Feb 22, 2024 by Tim Mills · across every show →

Everything said about transformer manufacturing facility, oldest first

Feb 22, 2024
Assertion Supported
Mills: Building a new transformer plant costs $100M and takes 1-2 years
“And then if you really had no equipment availability, and you had to add a new facility or a new line, you're talking hundreds of millions of dollars, well, hundred million dollars of investment in order to get that facility stood up. And then the lead time to…”
Tim Mills Feb 22, 2024 ▶ 17:58 The electric transformer shortage