Jun 13, 2024 neutral
Opinion
Janus: Standard 48-Hour Diesel Backup Is Probably a Data Center Relic
“I will say that backup is probably a bit of a relic because when we first started building these data centers, 15 years ago, most of them were relatively small. They were five or 10 megawatts. They were connected at distribution voltage. So the standard was pu…”
Brian Janous Jun 13, 2024 ▶ 19:09 Under the hood of data center power demand