Rob Gramlich, president of Grid Strategies, discusses policy measures designed to mitigate local opposition to electricity transmission line siting.
Opinion
Gramlich: Hyperscalers fundamentally require full grid connection for five-nines reliability
“My understanding from the hyperscalers and the data center developers is that they all really, really want the Full network transmission service with all of the good, you know, backup and cushion that that network provides to their operations, and the Five Nin…”
Insight
Gramlich: Utilities resist cheap grid tech because it hurts rate base returns
“Our utilities love their capital in the rate base. They don't love quite so much cheap things that can solve problems without a lot of capital in the rate base. So that's the problem with grid enhancing technologies.”
Prediction Not checkable as stated
Gramlich: US electric grid will face severe constraints for five years
“We're going to be, you know, putting a lot more both supply and demand on, and we're going to have a much more constrained grid, I think, for a good five years, and then depending on how long it takes us to build transmission, it could last longer.”
Prediction Partly held up
Gramlich: Electricity interconnection queue backlogs will not get worse
“I also don't expect the cues to get even worse than they are. I think there are a lot of activities to improve the cue processing issue.”
Assertion Partly supported
Gramlich: Only 55 miles of high-voltage transmission were built in 2023
“There were only 55 miles of new High voltage transmission lines in twenty-twenty-three, which is down, you know, a trickle from the 4000 you know, that had been built 10 years prior”
Assertion Supported
Gramlich: Energy Secretary Wright submitted a grid access rulemaking to FERC
“The Secretary of Energy, Secretary Wright, wrote this letter to FERC saying, you know, here's a rulemaking I'm putting before you, On access to the grid.”