Energy researcher Tyler Norris contextualizes the US power grid bottleneck, comparing the 2,000 GW queue backlog to the entire US operational fleet of 1,200 GW.
0:00 / 0:33exact quote · 33.3s
720p mp4 · rendered on demand · StarZero watermark
“So, in twenty-twenty-two alone, the backlog of projects in interconnection queues waiting to connect to the grid Grew by 40%. It brought the total to just over 2000 gigawatts. 80% of this growth, growth was driven by solar and storage projects, and for comparison, we have around 1200 gigawatts of generation capacity in the U.S. That's operational. So, of this 2000 gigawatts, 1350 around is generation capacity. Storage is about 700 gigawatts of that.”
quote is from the automated transcript, cleaned for reading:
filler sounds and stutters are removed, nothing is rephrased. names can be misheard
(the analysis reads context, assessments check outside sources). how →
More from Tyler Norris
AssertionSupported
Norris: 0.5% data center curtailment unlocks 98 gigawatts of capacity
“At 0.5% flexibility or curtailment of the new data center load, you could add up to 98 gigawatts of new data centers across the U.S. And at 0.25% curtailment of the new load, you could add 76 gigawatts.”
Tyler NorrisMar 27, 2025▶ 8:05The potential for flexible data centers
Opinion
Norris: Proactive transmission planning matters even more than interconnection queue reform
“The biggest Additional piece is improving the proactive transmission planning process and not relying as much on the interconnection process.”
Norris: AI data centers could drive 44% of US electricity load growth
“Yeah, I think what really opened our eyes were some of these forecasts suggesting that AI specialized data centers are going to be likely the single largest driver of U.S. Electricity load growth for the next five to seven years, with some numbers suggesting a…”
Tyler NorrisMar 27, 2025▶ 4:43The potential for flexible data centers
AssertionSupported
Norris: Roughly half of all US generation and transmission is unused
“And so what that basically means is that in any given hour,
On average, approximately half of all generation and transmission infrastructure is unused on average in the U.S., and it's actually worse than that because you're not counting for all the reserve ma…”
Tyler NorrisMar 27, 2025▶ 10:40The potential for flexible data centers
Opinion
Norris: Faster interconnection is the key value proposition for flexible data centers
“What would really present a value proposition for the hyperscalers and the large co-location data centers would be if you can actually interconnect them to the grid more quickly if they're able to offer this flexibility.”
Tyler NorrisMar 27, 2025▶ 14:37The potential for flexible data centers
AssertionSupported
Norris: Data center curtailment requires only partial load reduction in most hours
“When we ran the numbers, so like at that, that 0.25% load curtailment rate on average, we found that the number of hours in which Curtailment would be required. Some amount of curtailment would be 85 hours, but in 73 of those 85 hours, at least 50% of the new …”
Tyler NorrisMar 27, 2025▶ 19:32The potential for flexible data centers
Made with StarZero
Turn any episode into a week of clips.
This entire site, over 200 episodes transcribed, diarized, checked and made playable,
runs on the StarZero media pipeline. Drop in your own episode and the podcast clipper finds the
moments worth sharing, cuts them, captions them, and reframes them for every feed.
We use essential cookies to make the site work. With your permission we
also use analytics cookies (Google Analytics and Mixpanel) to understand
usage and improve StarZero. See our Cookie Policy.