Insight certainty 3/5 debate potential 2/5

Wong: Utilities adapt workflows to match legacy software limitations

Josh Wong · Can AI revolutionize grid operations? · Aug 20, 2026 · at 34:47

ThinkLabs CEO Josh Wong discusses why electric utility departments remain siloed and unable to integrate planning with operational execution.

0:00 / 0:12exact quote · 12.6s
720p mp4 · rendered on demand · StarZero watermark
“And so, in some ways, I would say the utilities are actually adapting their people and processes around the limitations of the analytics, intelligence, and decision-making frameworks that they have.”

quote is from the automated transcript, cleaned for reading: filler sounds and stutters are removed, nothing is rephrased. names can be misheard (the analysis reads context, assessments check outside sources). how →

More from Josh Wong

Assertion Not checkable as stated
Wong: ThinkLabs cuts nine-month grid interconnection studies to under 10 minutes
“So studies that would take previously nine months, right, as I mentioned, interconnection studies, now it takes us only a matter of a couple of minutes, like 10 minutes or less.”
Josh Wong Aug 20, 2026 ▶ 19:30 Can AI revolutionize grid operations?
Opinion
Wong: AI has higher potential upside in grid operations than planning
“I think it is the complete opposite. I think the potential is even higher.”
Josh Wong Aug 20, 2026 ▶ 28:54 Can AI revolutionize grid operations?
Opinion
Wong: The grid has enough latent capacity for most data centers today
“So let me just make a statement here, which is, I believe the grid has enough existing latent capacity to connect the majority, if not all of the data centers today.”
Josh Wong Aug 20, 2026 ▶ 37:27 Can AI revolutionize grid operations?
Assertion Supported
Wong: Transmission interconnection studies take 6-9 months and cost $250K
“I think most utilities are talking about six to nine months to perform one of those studies, and it's a one-time, right, so risk of restudies will compound that, and it does cost internal utility, typically a hundred, A couple of 100,000 dollars. The typical b…”
Josh Wong Aug 20, 2026 ▶ 11:07 Can AI revolutionize grid operations?
Assertion Partly supported
Wong: SCE projects up to 10,000 monthly energization requests taking 30-45 days
“I think when we public study that we did with SCE, I think they are projecting like up to 10,000 of these energization requests per month, and each one of them takes like 30 to 45 days.”
Josh Wong Aug 20, 2026 ▶ 12:44 Can AI revolutionize grid operations?
Assertion Not checkable as stated
Wong: ThinkLabs' physics-informed AI models are deterministic and cannot hallucinate
“So our models actually can't hallucinate. It's actually deterministic. You ask it the same thing, it will give you the same answer all the time.”
Josh Wong Aug 20, 2026 ▶ 17:35 Can AI revolutionize grid operations?
Made with StarZero

Turn any episode into a week of clips.

This entire site, over 200 episodes transcribed, diarized, checked and made playable, runs on the StarZero media pipeline. Drop in your own episode and the podcast clipper finds the moments worth sharing, cuts them, captions them, and reframes them for every feed.