electric vehicle charging depot

1 statements across 1 episodes · 0 bullish · 0 bearish · 1 people on the record · first statement May 15, 2025 by Neha Palmer · across every show →

Everything said about electric vehicle charging depot, oldest first

May 15, 2025 neutral
Insight
Charging infrastructure timelines mismatch with 6-to-12-month fleet vehicle procurement cycles
“That said, what's interesting is it takes us, call it, 18 months to 24 months to find a site, get it entitled, permitted, constructed, and then operational. Most vehicles make vehicle purchasing decisions at the most a year in advance, sometimes six months in …”
Neha Palmer May 15, 2025 ▶ 28:44 Terrawatt Infrastructure’s billion-dollar strategy