Jake Elder and Shayle Kann discuss the land and renewable resource potential for islanded, off-grid AI data centers.
0:00 / 0:26exact quote · 26.7s
720p mp4 · rendered on demand · StarZero watermark
“There was this foundational study that came out about two years ago that was co-authored by Stripe and Paces and Scale Microgrids, and they found over a terawatt of opportunity in the American Southwest alone, with high levels of renewable development being able to support those assets, like, 50% solar plus batteries at cost parity to using all gas and the ability to get up to, I think, 80 or 90% solar without a meaningful
Cost increase.”
quote is from the automated transcript, cleaned for reading:
filler sounds and stutters are removed, nothing is rephrased. names can be misheard
(the analysis reads context, assessments check outside sources). how →
More from Jake Elder
AssertionNot checkable as stated
Elder: Early off-grid data center projects fail to maintain 90% uptime
“When we, we've heard some of the early data from some of the off-grid projects that have been built so far, the ANIC data suggests they're not able to stay above even 90% uptime yet.”
Jake ElderMar 12, 2026▶ 20:43AI scaling pathways: on grid, on edge, off grid, off planet
AssertionNot checkable as stated
Elder: A 4-square-kilometer orbital data center would sustain hourly debris strikes
“If you scale that up to a single floating thing that's four kilometers, four square kilometers large, you can basically expect to have a piece of space debris hitting that you know, data center every hour.”
Jake ElderMar 12, 2026▶ 32:26AI scaling pathways: on grid, on edge, off grid, off planet
PredictionNot checkable as stated
Elder: Substantial AI model training will happen in space within 30 years
“In 20 years or 30 years, there's gonna be a lot of AI models being trained in particular in space”
Jake ElderMar 12, 2026▶ 38:40AI scaling pathways: on grid, on edge, off grid, off planet
AssertionSupported
Elder: Interconnecting gigawatt-scale data centers takes 5 to 7 years in many markets
“How, how long can we, how much time will it take to build out the transmission capacity necessary to interconnect these mega sites, gigawatt scale sites to new power supply, ideally, you know, carbon free power supply. And in many markets, right, that's runnin…”
Jake ElderMar 12, 2026▶ 5:55AI scaling pathways: on grid, on edge, off grid, off planet
Insight
Elder: Off-grid setups partially bypass generation bottlenecks with modular equipment
“The off-grid option in some ways maybe shortcuts the actual supply chain bottlenecks on the generation equipment side, at least to some extent relative to the other options. But I agree with you, there's still a bunch of other pieces of equipment, transformers…”
Jake ElderMar 12, 2026▶ 28:38AI scaling pathways: on grid, on edge, off grid, off planet
AssertionPartly supported
Elder: ISS rejects under 100 kW heat with soccer-field-sized radiator
“I think the whole International Space Station, for example, rejects less than a hundred kilowatts of heat in total, and they have a radiator the size of a soccer field, right?”
Jake ElderMar 12, 2026▶ 31:09AI scaling pathways: on grid, on edge, off grid, off planet
Made with StarZero
Turn any episode into a week of clips.
This entire site, over 200 episodes transcribed, diarized, checked and made playable,
runs on the StarZero media pipeline. Drop in your own episode and the podcast clipper finds the
moments worth sharing, cuts them, captions them, and reframes them for every feed.