“It's a lot faster to add capacity to the grid by just taking out old steel reinforced lines and replacing them with composite reinforced lines. You can get multiple times the capacity. I think two X is the number that I hear most hear quoted the most.”
quote is from the automated transcript, cleaned for reading:
filler sounds and stutters are removed, nothing is rephrased. names can be misheard
(the analysis reads context, assessments check outside sources). how →
More from Liza Reed
AssertionContradicted
Reed: External Transmission Can Support Under 1% of ERCOT Load
“And then ERCOT is incredibly isolated. So there's one or two ERCOT has some minimal Back to back and some minimal AC at sort of very low voltage, but incredibly isolated. I think less than one percent of their load or something is available via transmission. C…”
Liza ReedNov 3, 2022▶ 14:51Getting more energy on the wires
AssertionSupported
Reed: Non-ERCOT Texas avoided prolonged blackouts through grid interconnections
“And even the parts of Texas that were not run by ERCOT, especially, right, were experiencing this extreme weather, but did not have this massive multi-day blackout problem. Because they had so much more power available and were able to share it.”
Liza ReedNov 3, 2022▶ 20:21Getting more energy on the wires
PredictionNot checkable as stated
Reed: Decarbonizing the grid requires at least doubling transmission capacity
“The scale that we need to decarbonize the electricity system means we need to get twice as much transmission capacity or more. In the coming decades.”
Liza ReedNov 3, 2022▶ 38:32Getting more energy on the wires
AssertionSupported
Reed: Underground HVDC may cost only 1x to 2x of overhead lines
“There's some estimates out there that you might actually be closer to parity as opposed to the sort of five to 10 X that's normally cited. It could be closer to one to two X if you think about power over distance. So mile by mile you're more expensive, but gig…”
Liza ReedNov 3, 2022▶ 42:16Getting more energy on the wires
AssertionSupported
Reed: Utility regulations incentivize building new transmission over maximizing existing systems
“You can get a rate of return on new capital expenditures, which is new transmission lines, but you don't get that same benefit as an investor-owned utility for just maximizing what you already have in your system, right? In most places, right?”
Liza ReedNov 3, 2022▶ 34:37Getting more energy on the wires
AssertionSupported
Reed: Federal backstop authority for transmission line siting has never been used
“Transmission has always been permitted exclusively at the state level. There's been some very, very narrow federal authority established for it, but it's kind of this multi-step, elaborate process. There's a study, and then someone else has to review it, and t…”
Liza ReedNov 3, 2022▶ 54:07Getting more energy on the wires
Made with StarZero
Turn any episode into a week of clips.
This entire site, over 200 episodes transcribed, diarized, checked and made playable,
runs on the StarZero media pipeline. Drop in your own episode and the podcast clipper finds the
moments worth sharing, cuts them, captions them, and reframes them for every feed.
We use essential cookies to make the site work. With your permission we
also use analytics cookies (Google Analytics and Mixpanel) to understand
usage and improve StarZero. See our Cookie Policy.