Siegel: LS Power upgrades existing gas turbines for faster capacity additions

Paul Siegel · PJM and ERCOT navigate a capacity rollercoaster · Feb 12, 2026 · at 19:28

LS Power CEO Paul Siegel details his firm's bridge solutions to add generating capacity quickly before new power plants can be built.

0:00 / 0:18exact quote · 18.3s
720p mp4 · rendered on demand · StarZero watermark
“We're working on the conversion of some of our combustion turbines to combined cycle power plants that can be done more quickly than building something that's completely de novo. We have a project where we can swap out combustion turbine blades and get dramatically more capacity.”

quote is from the automated transcript, cleaned for reading: filler sounds and stutters are removed, nothing is rephrased. names can be misheard (the analysis reads context, assessments check outside sources). how →

More from Paul Siegel

Prediction Open · timeframe Jan 2030
Siegel: New large-scale gas power plants will not arrive before 2030
“Large scale gas is a 20, 30 plus new resource.”
Paul Siegel Feb 12, 2026 ▶ 19:12 PJM and ERCOT navigate a capacity rollercoaster
Assertion Supported
Siegel: The cost to build combined-cycle gas plants doubled or tripled
“Two, we've gone through this, again, very short period where prices for building a new large generation resource went from, let's say, for a combined cycle 10 years ago, we could build a new combined cycle for A little bit over a thousand dollars per KW. And t…”
Paul Siegel Feb 12, 2026 ▶ 14:44 PJM and ERCOT navigate a capacity rollercoaster
Opinion
Siegel: ERCOT forward market pricing cannot support new gas generation
“There was a big push through legislation to support new gas fire generation and ERCOT. I think if you look at forward markets, that's not supported by market pricing today. It may be supported by bilateral contracting opportunities, but when you look purely at…”
Paul Siegel Feb 12, 2026 ▶ 38:41 PJM and ERCOT navigate a capacity rollercoaster
Insight
Siegel: Battery saturation in ERCOT has compressed incremental investment returns
“A couple of years ago, we transitioned Intercut from a market that relies heavily on ancillary services to support batteries, and that was very robust. We built into that. That market was overwhelmed with supply, and then when you move out of the sort of small…”
Paul Siegel Feb 12, 2026 ▶ 39:09 PJM and ERCOT navigate a capacity rollercoaster
Assertion Supported
Siegel: PJM capacity prices surged from $30 to over $300 per megawatt-day
“When we rewind back just a couple of years, we had capacity clears that were going off between 30 and 50 dollars per megawatt day, and that compares to a little bit over 300 dollars a megawatt day in the more recent clears and subject to the cap in the capacit…”
Paul Siegel Feb 12, 2026 ▶ 4:16 PJM and ERCOT navigate a capacity rollercoaster
Insight
Siegel: Delivering large-scale gas generation takes four to five years
“And our planning horizons when it comes to large-scale gas-fire generation aren't measured in months. Today, I would say they're really measured over the course of four to five years between the realization that there's a need and all of the activities that ar…”
Paul Siegel Feb 12, 2026 ▶ 7:26 PJM and ERCOT navigate a capacity rollercoaster
Made with StarZero

Turn any episode into a week of clips.

This entire site, over 200 episodes transcribed, diarized, checked and made playable, runs on the StarZero media pipeline. Drop in your own episode and the podcast clipper finds the moments worth sharing, cuts them, captions them, and reframes them for every feed.