PREPA

0 statements across 0 episodes · 2 bullish · 3 bearish · 3 people on the record · first statement Jun 8, 2022 by Maria Gallucci · across every show →

Everything said about PREPA, oldest first

Jun 8, 2022 negative
Assertion Supported
PREPA signed a $1.5 billion gas infrastructure deal with New Fortress
“In twenty-nineteen, PREPA signed a 1.5 billion dollar contract with an American company called New Fortress Energy. To replace, ah, two of its oil-fired power plants with fossil gas, and kind of more controversially, to build an import terminal for liquefied f…”
Maria Gallucci Jun 8, 2022 ▶ 20:19 The tension over Puerto Rico’s energy future
Jun 8, 2022
Assertion Contradicted
PREPA laid off half its utility workforce before Hurricane Maria
“As a result of sort of those financial troubles, they had laid off half of their workforce.”
Maria Gallucci Jun 8, 2022 ▶ 3:31 The tension over Puerto Rico’s energy future
Jun 8, 2022 positive
Opinion
Grassroots groups drive Puerto Rico's renewable transition rather than utilities
“What you're seeing is that individuals, communities, nonprofit organizations are the ones that are really driving this effort toward a renewable, resilient power system, and not so much the government or the utilities.”
Maria Gallucci Jun 8, 2022 ▶ 5:13 The tension over Puerto Rico’s energy future
Jun 8, 2022
Assertion Supported
Utility PREPA entered July 2017 bankruptcy with $9 billion in debt
“The government had amassed over seventy billion dollars in debt, historic levels, and the utility itself was nine billion dollars in debt. In fact, they filed for bankruptcy in July, just months before the hurricanes hit.”
Maria Gallucci Jun 8, 2022 ▶ 3:18 The tension over Puerto Rico’s energy future
Jun 8, 2022 negative
Assertion Supported
Power outage durations doubled under privatized grid operator LUMA Energy
“In the fall of last year, there was some investigative reporting about what was happening to the grid under Luma, and one of the stats that grabbed me was that outage times have actually doubled under Luma. It's taking them longer to repair service than it did…”
Stephen Lacey Jun 8, 2022 ▶ 12:22 The tension over Puerto Rico’s energy future
Jun 8, 2022 negative
Assertion Supported
PREPA waited months to request mainland utility mutual aid after Maria
“Puerto Rico has that as well, but for whatever reason, for reasons that are unclear, PREPA did not initiate that process until months later.”
Maria Gallucci Jun 8, 2022 ▶ 9:24 The tension over Puerto Rico’s energy future
Jun 8, 2022 bullish
Prediction Partly held up
Citizen-driven solar in Puerto Rico will reach 1 gigawatt by 2025
“The fossil fuel industry still have a total control of PREPA, but we have done like a projection by 20, 25, Puerto Rico should be producing by net metering by citizenship. Citizen investment up to one gigawatt of power, which will be more than necessary for re…”
Arturo Massol-Deyá Jun 8, 2022 ▶ 19:05 The tension over Puerto Rico’s energy future
Made with StarZero

Turn any episode into a week of clips.

This entire site, over 100 episodes transcribed, diarized, checked and made playable, runs on the StarZero media pipeline. Drop in your own episode and the podcast clipper finds the moments worth sharing, cuts them, captions them, and reframes them for every feed.