French: New York's first offshore wind projects face 1-2 year delays

Marie French · New York’s clean energy puzzle · Nov 2, 2022 · at 7:55

Energy reporter Marie French details execution delays facing New York's first state-contracted offshore wind developments.

0:00 / 0:20exact quote · 20.4s
720p mp4 · rendered on demand · StarZero watermark
“These projects, you know, when they were first announced, the first two that have state contracts, when they were announced in twenty-nineteen by Governor Andrew Cuomo, you know, they were supposed to be online, I think twenty-twenty-four, May twenty-twenty-four and end of twenty-twenty-four for the two projects, and of course those dates are now twenty-twenty-five and twenty-twenty-six for them to actually be generating.”

quote is from the automated transcript, cleaned for reading: filler sounds and stutters are removed, nothing is rephrased. names can be misheard (the analysis reads context, assessments check outside sources). how →

More from Marie French

Assertion Supported
French: New York needs roughly 18GW of offshore wind for 2040 goals
“To actually achieve the state's, you know, ultimate twenty-thirty and twenty-forty goals We're going to need a whole lot more offshore wind than just nine gigawatts. We're going to need much more than that. I think the Climate Action Council, you know, support…”
Marie French Nov 2, 2022 ▶ 8:18 New York’s clean energy puzzle
Assertion Supported
French: NY climate law contains reliability off-ramps for 2040 target
“The climate law has off-ramps. The Public Service Commission, if it can, is concerned about reliability, Can, you know, be like, well, I guess we're not going to hit zero emissions by 2040.”
Marie French Nov 2, 2022 ▶ 19:50 New York’s clean energy puzzle
Assertion Supported
French: NYISO warned peaker plants may run longer if CHPE delays occur
“If Chippy the Champlain Hudson Power Express doesn't come online, you know, when it's currently forecasted to come online there could be some reliability issues that the NISO itself has said, you know, this could mean that the peakers need to stay on longer.”
Marie French Nov 2, 2022 ▶ 34:23 New York’s clean energy puzzle
Assertion Supported
French: New York's renewable siting office still staffing up after two years
“OREZ, the Office of Renewable Energy Siting, which is the new state office that was set up to do permitting and speed it up, essentially, for renewable developers, is still staffing up. And it's been two years. So, you know, we're still waiting.”
Marie French Nov 2, 2022 ▶ 9:25 New York’s clean energy puzzle
Insight
French: Battery storage cannot currently replace peaker plants one-to-one
“Well, I don't think batteries, right now, battery storage technology is not necessarily a one-to-one replacement for peakers, right? We don't necessarily have a battery that can run for several days or, you know, twelve-plus hours, and batteries need to rechar…”
Marie French Nov 2, 2022 ▶ 35:09 New York’s clean energy puzzle
Assertion Partly supported
French: Con Ed failed to award contracts in 300MW storage RFP
“Con Ed was required by the Public Service Commission to issue a utility scale request for proposals for battery storage. I believe, 300 megawatts was the target. I mean, other, other utilities were also required to issue RFPs, but they were like, you know, 10,…”
Marie French Nov 2, 2022 ▶ 14:19 New York’s clean energy puzzle