Jake Jurowicz, CEO of Blue Energy, cites Venture Global LNG as an operational precedent for using shipyard modular prefabrication to achieve commercial project financing.
0:00 / 0:16exact quote · 16.5s
720p mp4 · rendered on demand · StarZero watermark
“So they did this and it cut the construction time in half. It allowed them to fully project finance what was a first of a kind project down in Louisiana. And now they've done over thirty five billion in project finance this way and scaled it up very quickly.”
quote is from the automated transcript, cleaned for reading:
filler sounds and stutters are removed, nothing is rephrased. names can be misheard
(the analysis reads context, assessments check outside sources). how →
More from Jake Jurowicz
Opinion
Jurowicz: Gen-IV reactors solve problems the industry does not currently face
“The things, the problems that Gen-Fur reactors solve are not the problems we're faced right now, we're facing right now. We just need a lot of low-cost, affordable nuclear power. We don't have to reinvent the wheel.”
Jake JurowiczAug 12, 2026▶ 29:49Did someone just figure out how to project finance nuclear?
AssertionSupported
Jurowicz: Nuclear is the only power source enabling decades of fuel stockpiling
“You can actually safe harbor and stockpile years, even decades, of a nation's worth of fuel and energy in the form of uranium and nuclear fuel. You can't do that with any other power generation technology. You can't do that with gas. You can't do that with coa…”
Jake JurowiczAug 12, 2026▶ 7:52Did someone just figure out how to project finance nuclear?
AssertionSupported
Jurowicz: Nuclear power has never been commercially project financed
“Nuclear power has never been project financed before. It has always been financed on the backs of taxpayers and ratepayers because it's been so prone to construction risk.”
Jake JurowiczAug 12, 2026▶ 22:17Did someone just figure out how to project finance nuclear?
Disclosure
Jurowicz: Blue Energy will energize nuclear turbines early using natural gas
“We are gonna build half a nuclear plant. We're gonna build the whole nuclear balance of plant, the nuclear steam turbine system, and then we're gonna energize it early with the steam From two combustion gas turbines and their heat recovery steam generators. So…”
Jake JurowiczAug 12, 2026▶ 37:10Did someone just figure out how to project finance nuclear?
Insight
Jurowicz: New natural gas generation exposes AI providers to massive commodity risks
“Everyone's taking on an enormous amount of gas risk right now with all the new gas generation being built. Gas risk in the sense of gas is a volatile commodity in terms of price. Gas supply lines can be interrupted. If the EPA cracks down on emissions regulati…”
Jake JurowiczAug 12, 2026▶ 46:29Did someone just figure out how to project finance nuclear?
AssertionSupported
Jurowicz: Reactor equipment accounts for only 7% of nuclear build costs
“The reactor and the nuclear equipment are not the reason nuclear plants are expensive. If you look at historical data, it only represents about seven percent of the cost of historical builds.”
Jake JurowiczAug 12, 2026▶ 12:11Did someone just figure out how to project finance nuclear?
Made with StarZero
Turn any episode into a week of clips.
This entire site, over 100 episodes transcribed, diarized, checked and made playable,
runs on the StarZero media pipeline. Drop in your own episode and the podcast clipper finds the
moments worth sharing, cuts them, captions them, and reframes them for every feed.
We use essential cookies to make the site work. With your permission we
also use analytics cookies (Google Analytics and Mixpanel) to understand
usage and improve StarZero. See our Cookie Policy.